Tailings dam monitoring is the continuous measurement of a tailings facility’s condition, including pore water pressure, seepage, deformation, pond level and freeboard, so engineers can act on changes linked to credible failure modes before they become failures. Since the Global Industry Standard on Tailings Management (GISTM) took effect, it is also a requirement every operator must be able to demonstrate.
The stakes are clear from Brumadinho. In January 2019, Dam I failed in under five minutes, even though its survey monuments, inclinometers, ground-based radar and piezometers had not detected “any significant deformations or changes prior to failure” (Expert Panel). The lesson for your program is not to add more instruments. It is to cover the places your instruments can’t see, and the water that drives most failures.
In this article, you will learn what tailings dams are, why they fail, which failures shaped today’s rules, what GISTM requires, how every major tailings dam monitoring method compares, and how satellite soil moisture data helps you see the water that drives most failures.
Key Takeaways
- Tailings dams fail far more often than water dams. Over the past century, about 1.2% of tailings dams have failed, compared with about 0.01% of conventional water-retention dams.
- Water drives most failures. Seepage, overtopping, foundation weakness, and liquefaction from rising pore pressure account for most failures recorded in peer-reviewed studies.
- Monitoring is now a global requirement. GISTM establishes international expectations for tailings dam monitoring, with requirements linked to each facility’s credible failure modes.
- No single method sees everything. Piezometers measure pore pressure at points, Interferometric Synthetic Aperture Radar (InSAR) tracks surface movement, and L-band satellite analysis can help identify subsurface moisture anomalies associated with potential seepage, guiding engineers toward areas that require further investigation.
- Failures keep happening. Major tailings failures in Zambia (2025), Indonesia (2025 and 2026), Mexico (2026) and South Africa (2026) show the risk is current, especially at smaller, older and re-mined facilities.
What is a tailings dam?
A tailings dam is an embankment built to store tailings, the finely ground rock and process water left over after valuable minerals are extracted from ore. Tailings are pumped to the facility as a slurry. The solids settle, water collects in a pond, and the embankment is raised over the life of the mine as more tailings arrive. Unlike a water dam, which is built to full height before it fills, a tailings dam often grows for decades, and many are built partly from the tailings themselves.
How a tailings dam is raised has a major effect on its safety. There are three conventional methods, plus filtered (dry-stack) storage.
| Method | How it is raised | Pros | Cons |
|---|---|---|---|
| Upstream | Each raise sits on previously deposited tailings, moving inward toward the pond | Uses the least fill material; historically the most common design | Rests on loose, saturated tailings, so it is the most vulnerable to liquefaction; unsuitable for seismic areas and banned in Brazil, Chile, Ecuador and Peru |
| Downstream | Each raise is built on the outer slope of the previous section | Structurally independent of the tailings; behaves like a water-retention dam and can reach great heights | Needs large volumes of fill, and the footprint grows with height |
| Centerline | The crest rises vertically, partly on tailings and partly on the embankment | A balance of stability and material use | Cannot be used for large water-retention ponds |
| Filtered (dry stack) | Tailings are dewatered and stacked and compacted | Less free water to release; recommended as best available technology after Mount Polley | Still needs monitoring; a dry stack at Jaguar Mining’s Turmalina mine in Brazil slumped in December 2024 |
Sources: tailings.info; Franks et al., Scientific Reports, 2021; WISE Uranium Project; Earthworks, 2025 (upstream bans).
The data backs up the concern about upstream dams. In a study of 1,743 facilities disclosed by listed mining companies, active upstream facilities had the highest rate of past or present stability issues, at 18.3%, roughly twice the rate of active downstream facilities and six times that of active dry stacks (Franks et al., 2021). Both Brumadinho and Fundão, the two deadliest failures of the past decade, were upstream dams.
Why does tailings dam monitoring matter?
Tailings dam monitoring is the continuous measurement of a facility’s condition, including water pressure inside the dam, ground movement, seepage, water levels, and the state of the slopes, so that problems are found and acted on before they become failures. The scale of the challenge explains why it matters:
- 8,100+: Tailings facilities worldwide (conservative estimate); some estimates exceed 29,000 (Franks et al., 2021; World Mine Tailings Failures)
- 8.85B t: Tailings produced worldwide in 2016 (Global Tailings Review)
- 1.2%: Historical failure rate of tailings dams, vs about 0.01% for water dams (Azam & Li, 2010)
- ~2.5: Tailings dam failures per year on average (Piciullo et al., 2022)
No one has a complete inventory of the world’s tailings dams. Listed companies disclosed 1,743 facilities in 2019 and 2020, the dataset behind the Global Tailings Portal, but researchers estimate there are at least 8,100 worldwide, about 3,400 of them active (Franks et al., 2021). The volumes are huge and growing: the Global Tailings Review estimated in 2020 that about 11.1 billion cubic meters (14.4 billion tonnes) of additional tailings would need storage each year over the following five years.
Tailings dams also have no end date. Because tailings can stay unstable or toxic indefinitely, facilities must remain safe “in perpetuity,” and 10,000 years is a figure often used for how long these structures must keep their integrity (National Park Service). The consequences of failure last for years too. Brazilian authorities and the operators agreed settlements worth about R$37.7 billion for Brumadinho in 2021 and R$170 billion for Mariana in 2024, and in November 2025 the UK High Court found BHP liable for the Mariana collapse (BHP; Reuters via Claims Journal).
Why do tailings dams fail?
Most tailings dam failures come back to water: water pressure building inside the dam, water seeping through it, or water pouring over it. A review of historical failures by Lyu et al. (2019) found the leading causes were:
| Cause | Share of failures (Lyu et al., 2019) | How it develops | Examples |
|---|---|---|---|
| Seepage and piping | 21.6% | Water moving through the embankment or foundation carries particles away, saturates slopes and opens internal erosion paths | A contributing factor in many combined-cause failures |
| Overtopping | 20.6% | Heavy rain or poor water management raises the pond above the crest | Baia Mare, Williamson, Merriespruit |
| Foundation failure | 17.3% | A weak layer beneath the dam gives way under the load | Mount Polley, Los Frailes, Cadia |
| Earthquake | 17.0% | Shaking triggers liquefaction in loose, saturated tailings | El Cobre (Chile, 1965) |
| Other (including static liquefaction and structural causes) | 23.5% | Rising pore pressure in loose, saturated tailings causes a sudden loss of strength, often without warning | Brumadinho, Fundão |
Categories overlap, and many failures have more than one cause. Other studies rank slope instability, earthquakes and overtopping as the top three (Stark et al., 2022).
Static liquefaction deserves special attention. When loose, saturated tailings cannot drain, a small trigger can make them behave like a liquid. That is what happened at Brumadinho: the Expert Panel found the upstream dam had a steep slope, insufficient internal drainage, and a high water level, so the tailings stayed saturated and brittle until they suddenly lost strength. Height alone is not the risk factor it is often assumed to be. Lyu et al. found 85% of failures occurred at dams under 45 m tall, and in the disclosed-facility data, none of the 27 facilities taller than 140 m reported a stability issue (Franks et al., 2021). Water distribution and pore pressure are critical factors, but dam stability also depends on embankment design, drainage, material properties, and foundation conditions.
Rainfall is a growing pressure. Unusual rainfall is the leading cause of tailings failures in Europe (Rico et al., 2008), and many recent failures, from Indonesia to Mexico, followed heavy rain. Read more about how water affects mine safety in our guide to mine water management.
Which tailings dam failures shaped today’s rules?
The table below lists the landmark tailings failures that changed engineering practice and regulation. Volumes and death tolls vary between sources for several events, so we show the most widely cited figures.
| Year | Facility and location | Commodity | Released | Deaths | Cause and legacy |
|---|---|---|---|---|---|
| 1985 | Stava, Italy | Fluorite | About 200,000 m³ | 268 | Inadequate safety margins and drainage; ten people convicted |
| 1994 | Merriespruit, South Africa | Gold | About 600,000 m³ | 17 | Overtopping and wall breach after heavy rain |
| 1998 | Los Frailes (Aznalcóllar), Spain | Zinc, lead, copper | 4 to 5 million m³ | None reported | Foundation failure; toxic spill near Doñana National Park |
| 2000 | Baia Mare, Romania | Gold (cyanide) | About 100,000 m³ | None reported | Overtopping from rain and snowmelt; drinking water of more than 2 million people in Hungary affected |
| 2010 | Ajka (Kolontár), Hungary | Bauxite red mud | About 700,000 m³ | 10 | Dam failure; about 120 injured and red mud reached the Danube |
| 2014 | Mount Polley, Canada | Copper, gold | About 24 million m³ of tailings and water | None | A weak glacial clay layer in the foundation, missed by site investigations; led to calls for filtered tailings and independent review boards |
| 2015 | Fundão (Mariana), Brazil | Iron ore | Tens of millions of m³ (estimates vary) | 19 | Liquefaction of an upstream dam with drainage defects; pollution along more than 600 km of the Doce River |
| 2018 | Cadia, Australia | Gold, copper | About 1.33 million m³ | None reported | Embankment slump on a weak foundation layer; contained on site |
| 2019 | Brumadinho (Dam I), Brazil | Iron ore | About 9.7 million m³ | 270 | Static liquefaction of an upstream dam; led to Brazil’s ban on upstream dams and to GISTM |
| 2022 | Jagersfontein, South Africa | Diamond tailings (re-mining) | About 5 million m³ | 2 (1 missing) | Wall failure; a government investigation found the owner may have known of instability along the southern wall as early as 2019 (SAnews), and five people were sent to trial in 2025 (TimesLIVE) |
| 2022 | Williamson mine, Tanzania | Diamond | About 12.8 million m³ of water and tailings | None (3 injured) | Wall subsidence allowed water to overtop and breach the dam |
Main source: WISE Uranium Project, Chronology of Major Tailings Dam Failures (updated November 2026), with event-specific sources linked. For more depth on the Brumadinho and Mount Polley stories, see our analysis of 15 major dam failures.
Which tailings dams failed recently?
Tailings failures did not stop after Brumadinho. The WISE chronology lists 10 major tailings incidents in 2025 alone. Recent incidents demonstrate that tailings-related risks remain relevant across different facility types. Older and re-mined sites may present additional monitoring challenges. For the wider safety picture in mining, see our review of coal mine accidents and the lessons learned. Several are still under investigation.
| Date | Facility and location | What happened | Status |
|---|---|---|---|
| October 2026 | Sabinas mine, Zacatecas, Mexico | Tailings spilled after rain and spread about 13.6 km along a streambed to the Súchil River | Under investigation |
| August 13, 2026 | Dikwena chrome tailings facility, near Brits, South Africa | The northern wall of a tailings compartment collapsed and the tailings ran about 2 km, cutting mine access and bringing down power lines; the original facility had been re-mined from 2019 to 2022; no deaths reported | Under investigation |
| March 25, 2026 | Santa Fe mine, Sinaloa, Mexico | A sinkhole about 60 m wide opened in the tailings dam and mud flooded the underground mine; 2 miners died | Under investigation |
| February 18, 2026 | Indonesia Morowali Industrial Park (IMIP), Sulawesi, Indonesia | A landslide after heavy rain led to a nickel tailings dam failure | Under investigation |
| March 22, 2025 | IMIP, Sulawesi, Indonesia | A nickel tailings dam failed after heavy rain and flooded the industrial park; three workers buried | Documented |
| February 18, 2025 | Sino-Metals Leach, Chambishi, Zambia | About 50 million liters of acidic effluent entered the Kafue River basin; Kitwe’s water supply was shut | Litigation ongoing |
| December 7, 2024 | Turmalina mine, Minas Gerais, Brazil | About 750,000 m³ of a dry-stack tailings pile slumped; 255 residents evacuated | Documented |
Source: WISE Uranium Project unless linked. Details of 2026 events are preliminary.
What does GISTM require for monitoring?
The Global Industry Standard on Tailings Management (GISTM) was published in August 2020. It was developed through the Global Tailings Review, co-convened after Brumadinho by the International Council on Mining and Metals (ICMM), the United Nations Environment Programme (UNEP), and Principles for Responsible Investment (PRI). Its goal is zero harm to people and the environment.
The standard has 6 topic areas, 15 principles and 77 auditable requirements. For monitoring, the key point is that GISTM is performance-based rather than prescriptive. It does not tell you which instruments to buy. Instead, it requires “a comprehensive monitoring system” that supports the observational method, checks design assumptions, and tracks the credible failure modes of each facility, with clear trigger levels and responses. Other key requirements include:
- Consequence classification from Low to Extreme, based on what would happen downstream if the facility failed.
- Named accountability, including an Accountable Executive, a Responsible Tailings Facility Engineer (RTFE), and an Engineer of Record (EOR).
- Independent review by an Independent Tailings Review Board (ITRB) or senior independent reviewer for higher-consequence facilities.
- Regular reviews, with risk assessments updated at least every 3 years and dam safety reviews at least every 5 years for very high and extreme-consequence facilities (MDPI Minerals, 2024).
- Public disclosure of information about each facility, updated at least annually.
| Date | Milestone |
|---|---|
| August 2020 | GISTM published |
| August 5, 2023 | Conformance deadline for facilities rated Extreme or Very High consequence |
| January 21, 2025 | Global Tailings Management Institute (GTMI) launched to oversee independent audits and certification (UNEP) |
| August 5, 2025 | Conformance deadline for all other facilities |
| November 2025 | ICMM reports 67% of 836 member facilities fully conform, and more than 80% of Extreme and Very High consequence facilities (ICMM) |
| February 2026 | GTMI appoints Ed Toms as its first chief executive; its assurance framework is being set up (MINING.COM) |
What is a Trigger Action Response Plan (TARP)?
A TARP turns monitoring data into decisions. For each key indicator, such as pore pressure, displacement or seepage flow, the Engineer of Record sets threshold levels and agrees in advance what happens when each one is crossed. A typical structure looks like this (illustrative example only; your thresholds must come from your own facility’s design and failure modes):
| Level | What it means | Typical actions |
|---|---|---|
| Green (normal) | Readings within expected design range | Routine monitoring and reporting |
| Yellow (alert) | A reading departs from the expected trend | Increase monitoring frequency, inspect the area, notify the RTFE |
| Orange (alarm) | A threshold linked to a credible failure mode is crossed | Engineer of Record assessment, restrict deposition, prepare contingency measures |
| Red (emergency) | Failure is possible or underway | Activate the emergency response plan, warn and evacuate people downstream |
What should you monitor at a tailings dam?
A strong tailings dam monitoring program tracks the indicators linked to the facility’s credible failure modes. Most programs cover these six:
- Pore water pressure and phreatic surface. The single most important indicator. High pore pressure reduces the strength of tailings and embankment soils and drives liquefaction and slope failure. The International Commission on Large Dams (ICOLD) calls the position of the phreatic surface “vital” for tailings dams (ICOLD Bulletin 104).
- Seepage. Where water is leaving the facility, how much and whether it carries sediment, an early sign of internal erosion.
- Deformation. Settlement, bulging, cracking and slope movement at the surface and at depth.
- Pond level, freeboard and beach width. The margin between the water and the crest, and how far the pond sits from the embankment.
- Rainfall and water balance. Inflows and outflows, especially before and after extreme weather.
- Water quality. Contaminants in seepage, groundwater, and nearby streams.
Notice that four of the six are about water. That is why understanding where moisture is building up within and around a facility is central to tailings dam safety.
How do tailings dam monitoring methods compare?
The strongest programs combine in-situ instruments, inspections, and remote sensing, because each method covers a gap the others leave. Here is how the main tailings dam monitoring methods compare.
| Method | What it measures | Pros | Cons |
|---|---|---|---|
| Visual inspection | Cracks, seepage, boils, sinkholes, slumps, erosion, freeboard | Essential foundation of every program; catches what instruments miss | Periodic and subjective; Mount Polley failed without clear visual warning |
| Piezometers (standpipe and vibrating wire) | Pore water pressure and water table | The most direct indicator of liquefaction and slope risk; can send automatic alerts | Measures only at the points where they are installed |
| Inclinometers | Lateral movement and shear zones at depth | Shows the depth of movement | Borehole coverage only |
| Settlement plates and extensometers | Settlement and strain | Standard for tracking physical stability | Point measurements |
| Survey prisms and Global Navigation Satellite System (GNSS) | 3D surface position | High precision, can be automated | Point coverage |
| Seepage weirs and flow meters | Seepage flow rate | Tracks seepage and internal erosion trends | Only measures water that reaches the collection point |
| Ground-based radar | Surface movement | Near-real-time over a large face | Covers only what is in its line of sight |
| Satellite InSAR | Millimeter-scale surface movement over time | Wide area, with archives going back years | Shows movement rather than its cause; line-of-sight limits; revisit every 6 to 12 days |
| Drones, LiDAR (Light Detection and Ranging) and photogrammetry | 3D surface models, beach width, freeboard | Fast, detailed surveys | Surface only; slow trends are hard to see |
| Fiber-optic sensing | Distributed strain and temperature | Continuous over long distances | Must be installed within or along the structure |
| Satellite L-band soil moisture (ASTERRA EarthWorks) | Subsurface moisture and seepage up to 10 feet (3 m) deep | Maps where water is seeping and where ground is saturated across an entire facility, including hard-to-reach areas, and tracks change over time | Works alongside your instruments; ground teams are key to confirming what the data shows |
Sources: MDPI Minerals, 2024 (sensor technologies review); MDPI Minerals, 2024 (monitoring guidelines review); Rana et al., 2024; ASTERRA EarthWorks.
How does satellite monitoring help?
Satellites cover what point instruments cannot: the entire facility, its abutments and the surrounding hillsides, on a regular schedule and without anyone on site. Two kinds of satellite radar data are most useful, and they answer different questions.
InSAR shows where the surface is moving. Research on past failures shows both its promise and its limits. At Brumadinho, studies of European Space Agency Sentinel-1 data found movement on the dam face from early 2018, with acceleration from mid-December 2018 (Gama et al., 2020). A 2024 study of five tailings failures, however, found no precursor acceleration at Brumadinho, noted that earlier studies had found accelerating deformation at Cadia in the 2 to 3 months before it failed, and concluded that internal erosion and seepage cannot be reliably detected with InSAR (Rana et al., 2024). A 2026 retrospective study of Cadia found anomalous movement as early as January 22, 2018, about six weeks before the March 9 failure (ESA Copernicus). The consensus across these studies: satellite data is an early-warning and prioritization tool, used alongside in-situ instruments.
L-band soil moisture mapping shows where water is building up. Because seepage and saturation drive so many failures, knowing where an embankment, its toe, or a nearby slope is wetting up gives you a view that deformation data and point piezometers cannot. Longer L-band radar waves pass through vegetation and into the ground, so they respond to subsurface moisture rather than just the surface. Read more about measuring soil moisture from space. Learn more about how this works in passive vs active sensors and Synthetic Aperture Radar (SAR) sensor technology articles.
Satellite data is becoming more widely available. The NASA-ISRO Synthetic Aperture Radar (NISAR), a joint L-band and S-band radar mission of the National Aeronautics and Space Administration (NASA) and the Indian Space Research Organisation (ISRO), launched in July 2025 and began releasing free public L-band data on July 20, 2026 (Alaska Satellite Facility). NASA lists dams and levees among its applications (NASA).
Why do inactive and closed dams need monitoring?
Stopping deposition does not end the risk. Brumadinho’s Dam I had stopped receiving tailings in July 2016, about two and a half years before it failed. In the disclosed-facility data, about 58% of facilities are inactive, and these are often the sites with the weakest records and the least attention (Franks et al., 2021). Re-mining old tailings adds another risk, and it played a role at both Jagersfontein in 2022 and Dikwena in 2026.
Brazil shows the scale of the long-term challenge. Law 14,066/2020 banned upstream tailings dams and set a February 25, 2022 deadline to decommission them, but in January 2025 the national mining agency still counted 52 upstream dams in its program, with some completion dates running to 2035 (Agência Nacional de Mineração (ANM)). These dams need years of monitoring, often at remote sites with fewer staff. Wide-area remote monitoring helps you keep watch over inactive and closed facilities without a constant presence on site.
How does ASTERRA monitor tailings dams from space?
ASTERRA’s EarthWorks solution uses L-band polarimetric SAR from orbit to map subsurface soil moisture up to 10 feet (3 m) below the surface under suitable conditions. A single analysis can cover up to 64 km (40 linear miles) or 3,600 sq km (1,400 square miles), large enough for the biggest tailings facilities and the hillsides around them. The result is soil moisture maps that highlight areas of excess moisture and seepage, and by tracking changes over time you can see where conditions are changing.
Mine operators use EarthWorks to see where water is seeping from tailings dams and pipelines, collecting under roads and heavy equipment sites, and weakening hillsides. For tailings facilities, that helps your team:
- Find seepage and saturated zones across the whole embankment, toe, and abutments, including the areas between your piezometers.
- Prioritize inspections and instrumentation by sending engineers to the areas where moisture is building up.
- Track changes over time through wet seasons, raises, re-mining, and closure.
- Support your GISTM monitoring program with objective, repeatable data you can add to your performance monitoring and reporting.
Here are examples of projects that found success using ASTERRA. At a tailings dam in Scandinavia, EarthWorks showed positive results in monitoring dam performance and safety. As Eddy Segal, our VP of Sales and Business Development, explained, “subsurface moisture mapping can alert maintainers to a dam’s internal erosion a long time before any signs appear on the surface” (read the announcement). In 2023, EarthWorks for mines won the Successful Innovation Award at the Perumin 36 mining convention in Peru (read more). See how the same approach supports dams and levees and other critical infrastructure, or watch our webinar on monitoring tailings dams from space.
See where water is building up in your tailings facilities
Identify potential seepage and saturated zones across your tailings facilities, and use satellite moisture insights to prioritize field investigations.
Request a demo of ASTERRA’s EarthWorks solution
Frequently asked questions about tailings dam monitoring
What is tailings dam monitoring?
Tailings dam monitoring is the continuous measurement of a tailings facility’s condition, including pore water pressure, seepage, ground movement, pond level and freeboard, and water quality. Its purpose is to detect changes linked to credible failure modes early, so engineers can act through a Trigger Action Response Plan (TARP) before a problem becomes a failure.
What is a tailings dam?
A tailings dam is an embankment that stores tailings, the finely ground rock and process water left after minerals are extracted from ore. Many are raised in stages over the life of a mine and are built partly from the tailings themselves.
What are the three types of tailings dams?
The three conventional construction methods are upstream, downstream, and centerline. Upstream dams are raised on top of previously deposited tailings and are the most vulnerable to liquefaction. Downstream dams are raised on the outer slope and are structurally independent of the tailings. Centerline dams rise vertically as a compromise between the two. Filtered or dry-stack storage is a fourth approach.
How often do tailings dams fail?
Historically, about 1.2% of tailings dams have failed over the past century, compared with about 0.01% of conventional water dams. One study counted an average of 2.5 failures per year, and the WISE Uranium chronology lists 10 major tailings incidents in 2025 alone.
What is the most important thing to monitor at a tailings dam?
Pore water pressure and the position of the phreatic surface. High water pressure inside loose tailings reduces their strength and drives liquefaction and slope failure. Seepage, deformation, pond level, and rainfall complete the picture.
What is GISTM?
The Global Industry Standard on Tailings Management is the global standard for tailings safety, published in August 2020 by ICMM, UNEP and PRI after the Brumadinho disaster. It has 15 principles and 77 requirements, including a comprehensive monitoring system tied to each facility’s credible failure modes, independent review, and public disclosure.
Can satellites detect seepage from tailings dams?
Yes. L-band Synthetic Aperture Radar responds to moisture below the ground surface. ASTERRA’s EarthWorks solution uses it to map soil moisture up to 10 feet (3 m) deep and highlight areas of excess moisture and seepage across tailings facilities, so your team knows where to inspect first.
Which is the largest tailings dam in the world?
It depends on the measure. Syncrude’s Mildred Lake Settling Basin in Alberta, Canada, is often cited as one of the largest by volume of fill, with an embankment about 18 km around and up to 88 m high. Others are far taller: the tailings dam at the Antamina mine in Peru is being raised to 215 m, with a planned final height of 240 m.
References and further reading
| Source | Publisher | Used for |
|---|---|---|
| Report of the Expert Panel on the Technical Causes of the Failure of Feijão Dam I | Expert Panel, 2019 | Brumadinho failure mechanism, timeline and instrumentation |
| Global Industry Standard on Tailings Management | Global Tailings Review | GISTM structure and requirements |
| Tailings Progress Report 2025 | ICMM | GISTM conformance |
| New independent institute to drive implementation of global tailings standard | UNEP, January 2025 | GTMI launch |
| Tailings facility disclosures reveal stability risks | Franks et al., Scientific Reports, 2021 | Facility counts, construction methods, height and inactive facilities |
| Lessons from Tailings Facility Data Disclosures | Global Tailings Review, 2020 | Global tailings production and storage needs |
| A comprehensive review on reasons for tailings dam failures | Lyu et al., Advances in Civil Engineering, 2019 | Causes of failure |
| Tailings dam failure review | Mine Water and the Environment, 2024 | Failure rates (Azam and Li; Piciullo et al.) |
| Chronology of Major Tailings Dam Failures | WISE Uranium Project, updated November 2026 | Failure history, 1985 to 2026 |
| ICOLD Bulletin 104: Monitoring of Tailings Dams | ICOLD, via ASDSO | Monitoring priorities |
| Sensor technologies for safety monitoring in mine tailings storage facilities | MDPI Minerals, 2024 | Monitoring methods |
| A review of tailings dam safety monitoring guidelines and systems | MDPI Minerals, 2024 | Monitoring and review requirements |
| InSAR analysis of five tailings dam failures | Rana et al., Bulletin of Engineering Geology and the Environment, 2024 | Satellite precursors and limits |
| Gama et al. (2020) | Remote Sensing (MDPI) | Brumadinho InSAR analysis |
| Quarterly dam report, January 2025 | Agência Nacional de Mineração (Brazil) | Upstream dam decommissioning |
| Long-term risk of tailings dam failure | National Park Service, Alaska Park Science | Failure frequency and long-term design |
| Global Benchmarking of Mining Waste | Earthworks, November 2025 | Upstream dam bans |
| Seeing failure before it happens: satellite radar for tailings dam early warning | ESA Copernicus, August 2026 | Cadia InSAR precursor |
| Jagersfontein tailings dam owner “ignored structural instability warning” | SAnews (South African Government News Agency), December 2025 | Jagersfontein investigation findings |
| Five people to stand trial for Jagersfontein dam disaster | TimesLIVE, September 2025 | Jagersfontein prosecution |
| Global Tailings Management Institute appoints CEO and Technical Committee | MINING.COM, February 2026 | GTMI leadership |
| NISAR Applications: Levees and Dams | NASA | NISAR dam applications |
| NISAR L-band data now publicly available | Alaska Satellite Facility, July 2026 | NISAR data release |